Land reclamation works in HA. Dhidhoo are progressing steadily as planned, with 41 hectares reclaimed so far, accounting for 36.61 per cent of the overall project completion.The works are being carrie...
Mohamed Hilmy
25 January 2026, 00:00
Land reclamation works in HA. Dhidhoo are progressing steadily as planned, with 41 hectares reclaimed so far, accounting for 36.61 per cent of the overall project completion.
The works are being carried out by Leiv Eiriksson, a trailing suction hopper dredger with a capacity of 46,000 cubic metres. The vessel is currently undertaking dredging and reclamation operations to ensure the project remains on schedule.
The reclamation project is expected to significantly contribute to the development of Dhidhoo, particularly in supporting airport expansion, housing initiatives, and the provision of essential community infrastructure.
Maldives Airports Company Limited (MACL) commenced the land reclamation works in Dhidhoo on 5 January 2026. Once completed, the project is expected to enhance connectivity and improve living standards for residents in the area.
No comments yet. Be the first to comment!
News
Etihad Named Airline of the Year as MACL Launches Velana Awards to Elevate Maldives Aviation
13 Feb 2026
Opinion
BML Islamic Names 10 Winners in Hajj Promotion
12 Feb 2026
News
Rasmale’ Reclamation Nears Finish Line as 84% of Site A Completed
12 Feb 2026
News
President Muizzu Earns Global Health Spotlight in TIME100 Recognition
12 Feb 2026